FOUNDATIONS
Micropiles & Ground Anchors
Excavation shoring - 500 kV transmission lines - Uplift
A modern foundation system that delivers safety, versatility and fast installation.
We have the machinery required to install micropiles and anchors — self-drilling hollow-bar (AIA) system (Ischebeck TITAN System).
Micropiles and anchors are made of continuously threaded hollow bars. The bar is grouted with cement and serves simultaneously as the drill rod and as the tendon of the micropile or anchor.
• Safety, because it is a high-precision system that uses high-strength materials, so the expected results are achieved.
• Versatility, because it adapts to any type of load and is used in many different applications.
• Speed, because installation is fast: a single-pass procedure using rotary-percussive drilling with cement grout as the flushing fluid.
Installation requires only small-diameter boreholes, so compact rigs can be used and the environmental footprint is smaller than with other foundation techniques.
Safety, versatility and speed
• Tiebacks for excavation shoring.
They allow excavations to proceed safely, minimizing the risk of wall failure. The anchor is grouted as drilling advances, providing stability throughout the process.
• Anchors for 500 kV transmission tower foundations.
A fast, modern system that delivers safety, versatility and speed. It adapts to any load condition and minimizes construction time.
• Tiedown anchors against uplift.
Slabs — e.g. in wastewater treatment plants, underpasses and deep pits, especially below the water table — can be secured against uplift (buoyancy) with grouted TITAN micropiles.
Ground Anchors
Excavation shoring - 500 kV transmission lines - Uplift
Our projects
Paseo del Bajo - Buenos Aires
8,298 linear meters (27,224 ft) of TITAN 52/26 and 17,484 linear meters (57,362 ft) of TITAN 73/35.
ANCHORS ON 500 kV TRANSMISSION LINES
Our company has taken part in 6 of the 9 projects of Argentina's new 500 kV interconnection grid.
Córdoba 534 Building - Neuquén
Micropile shoring wall with 2 rows of TITAN tiebacks for a 7.0 m (23 ft) deep excavation housing 2 parking levels.